Timetable
Rosehill Recycled Water Scheme
- Dec 2005 – Tender process initiated by Sydney Water
- Nov 2007 – AquaNet named as preferred tenderer for the Project
- Aug 2008 – Execution of the Project Agreement between AquaNet and Sydney Water
- Jun 2009 – Licensing and other approvals in place
- Jun 2009 – Commence project construction
- May 2011 – Construction complete and commissioning to commence
- Oct 2011 – First water to flowed through the network to the foundation customers