Timetable

Rosehill Recycled Water Scheme

  • Dec 2005 – Tender process initiated by Sydney Water
  • Nov 2007 – AquaNet named as preferred tenderer for the Project
  • Aug 2008 – Execution of the Project Agreement between AquaNet and Sydney Water
  • Jun 2009 – Licensing and other approvals in place
  • Jun 2009 – Commence project construction
  • May 2011 – Construction complete and commissioning to commence
  • Oct 2011 – First water to flowed through the network to the foundation customers